Bizzack Construction Leads Vital Corridor Q Work : CEG

2022-09-24 02:50:21 By : Mr. Hooray He

Thu September 22, 2022 - Northeast Edition #20 Chuck MacDonald – CEG CORRESPONDENT

Virginia Department of Transportation (VDOT) is partnering with Bizzack Construction and subcontractors to build an updated road system that will improve regional connectivity and generate economic development in relatively isolated areas. Corridor Q (Route 460) will provide residents with better access to healthcare, improved travel times and increased interstate commerce opportunities.

Corridor Q will extend from the Kentucky state line to existing U.S. Route 460 in the town of Grundy, Va.

The massive undertaking means workers taking on many challenges including cutting through mountains and relocating the dirt and rock into support for the new highway. Corridor Q will provide a safer two-lane highway with truck climbing lanes. Workers will use large-scale equipment to move more than 15 million cu. yds. of material in just three years on a 2-mi. construction segment, Poplar Creek Phase B.

Corridor Q also has challenged engineers, field workers and planners alike as they built the tallest bridge in the state (Route 460 Connector Phase 1), will soon build the second tallest bridge in the state (Poplar Creek Phase B), built the deepest segmented, precast box culvert (Poplar Creek Phase A) in Virginia and will construct the deepest earth cut in the state (Poplar Creek Phase B).

This massive endeavor is composed of several smaller jobs, each of which would be a significant project on its own. The estimated cost for the entire 14.2-mi. project will be around $750 million.

Marty Halloway, VDOT Bristol District Mega-Projects engineer, leads a team from various locations to coordinate these efforts.

"The current roads in this region are mountainous, two-lane roads," said Halloway. "Corridor Q will be safer with a significant reduction in travel time."

Blasting and drilling were vital to produce the deepest cut in the state, nearly 500 ft. deep.

"The Poplar Creek Phase A cut was the deepest cut, but only one of many necessary for this project," said Halloway. "Our contractor used large-scale equipment to move enormous amounts of material more quickly than would have been possible in the past. Work teams also used onsite material to create the embankments and fill."

The Corridor Q project required huge amounts of building materials including 35,000 tons of asphalt. Some 16,000 cu. yds. of concrete were necessary for just the Phase 1 bridge. An onsite concrete batch plant was used for the bridge. Workers planned to finish the pavement with a 6-in. base mix and 1.5-in. asphalt concrete pavement 12.5D surface. The roads will have 13-ft.-wide shoulders.

The Phase 1 bridge, the tallest in Virginia, was built over Grassy Creek.

"The bridge construction topped out at 250 feet above the creek," said Halloway.

The bridge was built of twin 1,700-ft.-long cast-in-place segmental bridges, each with a deck width of 43 ft., carrying two lanes of traffic in each direction.

Workers will take on another daunting challenge with the Poplar Creek Phase B project. When constructed, this will be the second-tallest bridge in the state at 150 ft. tall, just over 1,000 ft. long and containing a 338-ft. span.

Deep ravines created another problem for designers and workers. Stream impacts required some original thinking. The team solved the problem by building the longest segmented pre-cast box culvert in the state on the Poplar Creek Phase A project. The culvert needed to withstand 310 ft. of embankment fill on top of it and still be able to carry water to the proper channel.

"There was no template to use for designing such a culvert with that kind of stress and strain present," said Halloway. "Our team studied the various factors that would be on the culvert and made sure to design it properly. At one point we undercut an additional 25 feet of material to reach bedrock to make sure the culvert would be properly supported. Then, we put the temporarily relocated stream back into the box. We calculated that it would be sufficient to convey a 100-year flood, even while partially obstructed."

Not only did the team manage challenging geography, but communication was unique as the team was spread out from Maryland to Virginia and from Kentucky to Illinois.

"We had to rely on virtual collaboration and do much of the work virtually before and during the pandemic," said Halloway.

In addition, the teams had to contend with labor issues and supply chain challenges that are common in today's construction environment.

"We also had environmental challenges, utility schedules and permitting issues to work around."

Halloway is looking forward to the day when motorists will be able to use the new road in its entirety.

"In the end, I believe travel will be faster and safer. Travel will be much easier locally and to other states."

On average, the contractors use 120 pieces of equipment on the Poplar Creek Phase A construction project at any given time. The Intersection Hawks Nest paving project has approximately 35 pieces of equipment. This includes everything from pickup trucks to large, off-road equipment.

Concrete Sector Continues to See Project Delays, Production Cut-Backs

Atkinson Moves Mountains On California Highway Project

Uncommon MSE Wall Failure Calls for Unique Geotechnical Solutions

Bobcat Unleashes T86 Compact Track Loader, S86 Skid Steer Loader

Texas AGC Lauds Record $85B in Funding

Case E Series Excavators Reloaded With Major Evolution in Operator Experience

American Cancer Society to Host Big Dig Denver's 2nd Annual Event

Raised On Blacktop With American Pavement Specialists

Construction Equipment Guide 470 Maryland Drive Fort Washington, PA 19034 800-523-2200

Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.

Contents Copyrighted 2022, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication. Read our privacy policy here.